Commissioning @ TJB 5&6 Jepara

Updated: Apr 27, 2021



  • Project detail of power plant

Tanjung Jati B power station is a 2,640 megawatt (MW) coal-fired power station located in Central Java Province, Indonesia. A third phase of two 1000 MW units is described in PLN's long-range plan for 2013-2022. It is referred to as "PLTU Jawa-4 #5 and #6" and is slated for 2019 and 2020. In March 2020 the project's sponsor announced that it might be delayed as a result of the COVID-19 pandemic. Construction of Units 5 and 6 was reportedly 93% complete as of May 31, 2020

○In June 2021 the project will fired up the first time for the Unit 5

  • Project detail of unit

The H2 generator system specifications are 2x100% HMXT200 one unit as a backup unit and also with 7 cradles consist of 36 cylinders as a backup supply or high demand. Flow is 2x11.2nm3/hr H2 99,9999% purity. .

  • Commissioning schedule

Started November 2020 to February 2021, longer days was taken as couple of restriction from the government.